Activity | Location | Date | Status |
Road paving | Bird Rock Road, Basseterre | July 12, 2025 | Complete |
Road patching | Pomp Bay, Sandy Point | July 13, 2025 | Complete |
Road patching | Side street adjacent to Bourkes Road, Sandy Point | July 14, 2025 | Ongoing |
Drain Work | George Street, Basseterre | July 14, 2025 | Ongoing |
The R&D thanks the public for its patience and cooperation.