Schedule PWD: Timeline for Constructing a Retaining Wall at Pump Bay, Sandy Point By: James Morris Date: July 23, 2024 Share post: FacebookTwitterPinterestWhatsApp Activity – July 25 & 26 – Casting of concrete flooring. July 29 – August 7 – Laying of blocks. August 8 & 9 – Backfilling and cleanup. Time & Location – July 15, 2024 (9:00 am) – August 9, 2024 (3:00 pm) Pump Bay, Sandy Point Previous articleProperty Condition Survey for East and West Shadwell to Begin June 29, 2024Next articlePWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill Latest Articles WSD Activity for Tuesday, July 1, 2025 James Morris - July 1, 2025 PWD Roads and Drains Division Activity for Tuesday, July 1, 2025 Public Works Department Energy Transition Unit, New AMI System among SKELEC’s 2025 Highlights Events Related articles Schedule PWD: Timeline for Clearing Debris and Bush at the South East Peninsula Activity -The team will be clearing the road of debris and overhanging bushes. Drivers are asked to exercise... Public Works Department Daily Tracker for PWD’s Asphalt Crew Nature of Work:The asphalt crew will be cleaning storm drains.When & Where:July 23, 2024 (9:00 am) - July... Schedule PWD: Timeline for Demolishing and Casting Concrete Drains in Lower Monkey Hill Activity -The crew completed the right side of the drain prior. They will focus on the left side.Time...